A client offers ¥1.2 million for a booking-system update by the end of the month. Before you answer, open both the estimate and the delivery team’s calendars. Here’s how the decision plays out on an illustrative project. All figures exclude tax.
1. How much gross profit does the quote leave?
Assume internal labour costs ¥5,000 an hour, the job needs 120 staff-hours and subcontracting will cost ¥120,000. Deduct ¥600,000 in labour and ¥120,000 in subcontracting from the ¥1.2 million fee. Estimated gross profit is ¥480,000, a 40% margin, before company overheads such as rent and sales expenses.
2. Where will the hours go?
Break the 120 hours down: 16 for requirements, 24 for design, 56 for implementation and 24 for testing and fixes. Suppose a change to the rescheduling rules adds 20 staff-hours after delivery. Without an extra fee, that costs ¥100,000, leaving ¥380,000 in gross profit and a margin of about 31.7%.
Define the boundary in the quote. For example, fixing a deviation from the approved specification is included; a change to that specification gets a new estimate before work starts. Ask sales and delivery to explain the rule to the client using the same example.
3. Who actually has time before the deadline?
The team may have 120 hours free overall, but if the developer has only 40, implementation alone is short by 16 hours. A tester’s availability won’t automatically fill that gap. List the owner, required hours and available hours for each week to see who needs to discuss the deadline and when.
A checklist for the next project review
- Estimated gross profit: fee [ ] − internal labour [ ] − subcontracting and other direct costs [ ] = [ ].
- Effort: which task could change the estimate? [ ] Gross profit if it takes [ ] extra hours: [ ]. A new quote is triggered when [ ].
- Capacity: role and week with a shortfall [ ]; hours missing [ ]. What to negotiate, who will do it and by when [ ].
For this project, the decision can be specific: check whether 16 hours of development can be booked next month and discuss the delivery date with the client. Crocolla’s published case study of a software contractor describes introducing project reviews alongside a dashboard showing staff utilisation. At your next review, take one live quote and compare it with the actual calendars.